Forest Lake Christian School
Job Scope: 2008 New Construction
Combie Road
Auburn, California
This 13,800 square foot classroom/gymnasium facility added six large state-of-the-art classrooms and a gymnasium for indoor Physical Education classes and the Jr. High after school program. This was a prefabricated structure that required the coordination of the manufactured building and the layout of the footings, slab and embedded items. While the building was being erected crews worked diligently inside the structure framing walls and installing the various building components. Efficient teamwork enabled this project to be completed in an unbelievable 26 weeks, start to finish!
Toward the end of the project, church members and scouting programs worked to construct a play area for the Combie Bible Church. Their efforts, combined with a donation from Wells Construction, enabled the installation of safe playground equipment for the children in the Sunday School program. The end result is an energy efficient, functional building.


Wells Construction's Network